Step 01Week 1
Charter and choose the pilot area
Bound the work so it can succeed visibly before it is scaled.
- Name an executive sponsor, a 5S leader, and an area champion who works in the area.
- Pick one pilot area small enough to finish and visible enough to matter.
- Baseline the area: photographs from fixed positions, search-time samples, safety findings, downtime.
- Write a one-page charter: problem, measurable goal, dates, and who decides.
Output — Signed charter, baseline pack, and a pilot area with a named owner.
Step 02Week 1-2
Train the team on the work, not the theory
Everyone who touches the area understands the five steps and their part.
- Run a 60-90 minute session on the floor, in the area, using the real workstation.
- Walk the current state together and let the team name what gets in their way.
- Agree on the audit rubric before the first S — the standard is defined up front.
Output — Trained area team, agreed rubric, and a list of the team's own irritations.
Step 03Week 2
Sort and red-tag
Get everything unnecessary out of the area, with decisions closed.
- Red-tag event with the whole area team present; tag everything not needed for current work.
- Stage red-tagged items with an owner and a decision date, not an open pile.
- Close every tag: return, relocate, repair, or dispose — and record what it freed up.
Output — Cleared area, closed red-tag log, and recovered space and dollars quantified.
Step 04Week 3-4
Set in order and shine
Design the layout around the work, then clean to inspect.
- Locate what remains at point of use, in the sequence of the job; label and outline every location.
- Set min/max quantities and visual triggers for replenishment.
- Run the first clean-to-inspect pass and log every abnormal condition found.
- Fix at the source: contain leaks and correct root causes rather than scheduling more cleaning.
Output — Visual layout, marked locations, and an abnormality log with owners and dates.
Step 05Week 4-5
Standardize the best known way
Write the standard down and post it where the work happens.
- Document standard work, layout, and cleaning schedule on one page per station.
- Post the standard, the owner's name, and the audit score at the area board.
- Define how the standard changes — revision control, not verbal workaround.
Output — Posted standard work, area board, and a controlled revision process.
Step 06Week 6 onward
Sustain through cadence and audit
Convert a good week into a permanent operating condition.
- Daily: 5-10 minutes of 5S at shift end, built into the schedule, not added to it.
- Weekly supervisor audit, monthly manager audit, quarterly executive walk — published dates.
- Post scores and trends; every gap gets an owner and a date; recognize areas that hold.
Output — Audit trend line, closed-gap log, and a cadence on the leadership calendar.
Step 07Quarter 2 onward
Replicate and renew (ARC™)
Standardize what worked, then raise the standard.
- Convert the pilot into the site playbook: rubric, board layout, standard-work format.
- Sequence the next areas; use the pilot team to coach rather than a central staff group.
- Reassess quarterly against a higher standard — the bar moves as capability grows.
Output — Site playbook, rollout sequence, and a higher rubric for the next cycle.
Training venue
Assess your 5S situation right now, then plan and prove the improvement
The full working session lives on its own page so this one stays readable: a five-level rubric for each S, a target one level up, the first-pass plan, the Red Tag event, and the before-and-after measures — printed as your training material and as the evidence of what changed.
Who owns what
Executive sponsor
Removes barriers, funds the work, walks the area quarterly.
5S leader
Coordinates training, rubric, schedule, and the rollout sequence.
Area champion
Owns the standard in the area and the daily discipline behind it.
Operators
Perform daily 5S, surface abnormalities, and improve the standard.
Supervisors
Audit weekly, coach the gap, and close findings with dates.
Maintenance
Fixes at the source and partners on clean-to-inspect findings.
Audit rubric
- Level 1Area cleared and red-tag log closed.
- Level 2Locations labeled; everything has one obvious home.
- Level 3Clean-to-inspect running; abnormality log active with owners.
- Level 4Standard work posted and followed across all shifts.
- Level 5Audit cadence held for a full quarter with a rising score.
Score weekly, post the trend, and give every gap an owner and a date.
Why 5S programs fail
- 01Launching everywhere at once instead of proving it in one area first.
- 02Treating Shine as cleaning instead of inspection — abnormalities never get logged.
- 03No published audit cadence, so the standard decays as soon as attention moves.
- 04Scores posted with no owner or date attached to the gaps.
- 05Adding 5S on top of a full schedule rather than designing the minutes into the shift.
- 06Leaders who inspect the area but never work the standard with the team in it.
Executive takeaway
5S creates the everyday discipline required for safety, flow, ownership, equipment reliability, and scalable growth. Architecture determines performance — 5S is where that architecture becomes visible on the floor.